Unanimous orders pause an air-permit proceeding and emergency well authorization while New Mexico’s Supreme Court considers separate legal challenges
By ROGER M. RAEL
THE RATON RANGE
SANTA FE, N.M. — The New Mexico Supreme Court has temporarily halted two state actions connected to Project Jupiter, the massive artificial-intelligence data-center development under construction near Santa Teresa.
In separate unanimous orders issued Aug. 23, the five justices stayed an air-quality permit proceeding and suspended an emergency authorization allowing water from a newly drilled well to be used during construction.
The orders do not decide either legal challenge, reject the air-permit application or shut down the entire Project Jupiter construction site. They freeze two specific regulatory actions while the court considers what happens next.
The first case was brought by Santa Fe-based New Energy Economy against the New Mexico Environment Department and other state officials.
The Supreme Court stayed the administrative proceeding involving Yucca Growth Infrastructure LLC’s application for Air Quality Permit No. 10883. The application covers a proposed microgrid that would use natural-gas-powered fuel-cell technology to generate electricity for the data-center complex.
A public hearing had been scheduled to begin Sept. 14.
New Energy Economy argues that the accelerated schedule, denial of discovery and delayed release of the administrative record prevented opponents from adequately examining technical evidence before submitting testimony.
The organization is seeking a writ of mandamus directing state officials to provide what it contends are legally required due-process protections.
The Supreme Court’s order does not decide whether those allegations are correct. It simply freezes the underlying proceeding while the justices examine the petition.
The respondents may file answers by Sept. 2. No reply may be filed unless requested by the court.
The second order concerns water.
In a case brought by the Center for Biological Diversity against State Engineer Elizabeth Anderson, the court stayed an Oct. 23, 2025, emergency drilling authorization permitting water from a new well to be used for Project Jupiter construction. Santa Teresa Capital LLC is identified as the real party in interest.
That authorization will remain suspended until further order of the court. A response is also due Sept. 2.
The Center for Biological Diversity alleges the state engineer approved the replacement well without providing the public notice and hearing required under New Mexico water law. The organization reported that more than 103 million gallons had been pumped from the well since April.
Those remain the organization’s allegations. The Supreme Court has not ruled on whether the state engineer acted unlawfully.
Chief Justice Julie J. Vargas and Justices Michael E. Vigil, C. Shannon Bacon, David K. Thomson and Briana H. Zamora concurred in both orders.
WHY RATON IS WATCHING
The southern New Mexico cases are drawing attention in Raton because residents here have raised similar questions about water availability, air emissions, electricity generation, noise, utility costs and public access to information surrounding any future data-center development.
The court cases do not establish a connection between Project Jupiter and any potential Raton project. They do, however, demonstrate how quickly unresolved permitting and public-participation disputes can reach the state’s highest court.
Raton-area residents monitoring data-center development provided The Raton Range with copies of the legal filings and Supreme Court orders Monday morning.
John Scott Foreman previously identified the local neighborhood organization as Protect Our Resources, or POR, during comments before the Raton City Commission. He said the organization supports sensible safeguards intended to protect Raton’s small-town character and surrounding environment.
Julia Davis Stafford, a lifelong Colfax County resident associated with the C.S. Ranch, separately warned commissioners that ranching operations between Cimarron and Raton rely on meters connected to Raton’s water system. She questioned whether future data-center demand could threaten that reliability during severe drought.
The two Project Jupiter orders provide an important lesson for communities considering large industrial developments: Questions involving water, electricity, air pollution and public participation are easier to address before approvals are granted than after construction begins and the dispute reaches the Supreme Court.
Project Jupiter has not been defeated. Its entire construction operation has not been shut down.
But on two significant regulatory fronts, New Mexico’s highest court has told the state to stop and wait.
Editor’s note: The copy of the air-quality order reviewed by The Raton Range contains an apparent clerical date discrepancy. Although the order requires a response by Sept. 2, 2026, its certification section states that the court’s seal was affixed Oct. 23, 2026. Contemporary reporting identifies the order as having been issued Aug. 23. The discrepancy does not alter the stay language, but clarification should be sought from the Supreme Court clerk.
SOURCES
- New Mexico Supreme Court orders in New Energy Economy v. New Mexico Environment Department and Center for Biological Diversity v. Elizabeth Anderson, copies provided to The Raton Range by Raton-area residents monitoring data-center development.
- New Mexico Environment Department — Yucca Growth Infrastructure LLC, Air Quality Permit Application No. 10883
- Center for Biological Diversity — Aug. 20 emergency-petition announcement
- Center for Biological Diversity — Aug. 24 response to the Supreme Court stay
- Organ Mountain News — Supreme Court puts Project Jupiter air and water actions on hold
- New Mexico Courts — Supreme Court jurisdiction and information
- Public comments delivered to the Raton City Commission by John Scott Foreman and Julia Davis Stafford and reviewed by The Raton Range.